XXX 土建工程

洞门破除专项方案

编制:

审核:

批准:

XXX 有限公司 XXXXXXXX 标项目部

XXXX 年XX 月XX 日

目 录

1、编制目的及编制依据 ········································································ 3

1. 1编制目的 ·················································································· 3 1. 2编制依据 ·················································································· 3 2、洞门破除施工进度安排 ···································································· 3 3、洞门破除施工工艺 ············································································ 3

3. 1 围岩判断 ················································································· 3 3. 2 洞门破除尺寸 ·········································································· 3 3. 3 施工步骤 ················································································· 4 4、质量保证措施 ··················································································· 5 5、安全保证措施 ··················································································· 5

洞门破除方案

1、编制目的及编制依据

1. 1编制目的

为确保盾构机始发时的洞口土体稳定,使盾构机安全、平稳、迅速地由盾构始发井进入隧道,防止洞门处土体坍塌及洞门漏水,特制定此施工方案。

1. 2编制依据

(1)盾构机图纸,盾构机使用维护技术文件; (2)盾构始发井主体结构设计图;

(3)《岩土工程勘察报告》,《岩土工程补充勘察报告》; (4)其它相关技术文件及图纸等。

2、洞门破除施工进度安排

洞门破除施工与盾构机组装、调试同时进行。为避免洞门暴露时间过长而失稳,应确保洞门破除完成的时间,和盾构机始发的时间相差48小时以内。右线洞门破除施工用时10天,开始时间为10月下旬,早于左线始发10~12天。左线线洞门破除比左线推迟一个月,用时亦为10天。

3、洞门破除施工工艺

3. 1 围岩判断

始发端头处隧道拱顶覆土约5.5m ,有、、地层,如图1所示。隧道全断面为富水砂层,洞门处地质围岩条件比较差。但是始发端头采用旋喷桩加固了12m 长,根据抽芯检查结果洞门处地质围岩条件已经改良、非常稳定,洞门的破除不会对周围土体和围岩产生大的影响。

3. 2 洞门破除尺寸

始发井围护结构采用地下连续墙,墙内布置有钢筋,考虑到刀盘外径和洞口止水装置的尺寸要求,故洞门破除外径定为6500mm ,洞门破除采用人工破除。施工前准确定位隧道洞门中心线,然后对洞门内进行开凿放样。洞门尺寸如图2所示。

图1

图2 洞门破除尺寸图

3. 3 施工步骤

洞门破除分两次完成,先凿除围护结构至墙体外侧钢筋,留下内侧钢筋及保护层以保证掌子面安全;当盾构机组装、调试完成后,准备始发时,割除围护结构内侧钢筋,盾构机迅速推进至土体。

洞门凿除施工时,在盾构机与掌子面之间搭钢管支架,利用人工进行凿除围护结构施工。第一步:凿除外层钢筋砼,直至留下最后一层钢筋,凿除范围和分

块方法按下图所示。凿除方法是先凿竖向和横向4道沟槽,再凿环向沟槽,分块沟槽宽度约为180mm ,如图3所示。凿除顺序按分块编号顺序,从上往下顺序凿除。计划安排6名工人,从盾构机主体组装之时开始凿除,在一周内完成凿除任务。第二步:剩余部分钢筋砼凿除时间定在盾构机掘进之前,凿除时加大人力投入,迅速破除洞门,确保盾构机安全进入。破除工作保证围护结构地下连续墙的钢筋全部切断,以避免盾构推进时刀盘被未切断的钢筋挂住。

图3 洞门凿除方法示意图

凿除施工完毕后拆除脚手架,快速拼装负环管片,使盾构机刀盘顶住掌子面,避免掌子面暴露太久发生失稳坍塌。

洞门破除施工工艺流程图见图4。

图4 洞门破除施工流程图

4、质量保证措施

⑴施工制作前,有关技术人员应熟悉图纸,施工前向施工班组进行技术交底。 ⑵在洞门边缘处用风镐开凿时,风镐应从圆形洞门轮廓线上向圆心方向斜向插入,小块凿除,防止洞边混凝土崩裂。

⑶控制洞门凿除尺寸不小于Φ6500mm.(盾构机刀盘最大直径为6280mm ,按允许隧道轴心线最大偏差为50mm 计,则刀盘能通过的理论最小直径为6380mm ,考虑刀盘与切割的钢筋头之间预留50mm 安全间隙故将洞门混凝土破除范围定为Φ6500mm) 。

5、安全保证措施

⑴对各施工人员进行安全意识教育和操作规程教育。 ⑵进行施工作业之前应组织相关人员进行安全技术交底。

⑶井下施工人员均应正确佩带好安全防护设施, 及时避让混凝土块。 ⑷进行高空作业必须和地面人员协调好,禁止抛掷工具。

⑸脚手架搭设应牢固可靠, 并应加设足够支撑或拉杆以保证其稳定性。 ⑹委派专门的技术人员对现场施工进行技术和安全指导。

⑺密切注意掌子面的稳定和失水情况。若发现掌子面不稳定,应立即清理支架,撤离作业人员。推进盾构机顶住掌子面。


相关内容

  • 洞门破除方案
    天津地铁六号线土建工程17标 鞍山西道站-天拖站-一中心医院站-红旗南路站盾构区间洞门凿除施工方案 编 制: 校 对: 审 定: 中煤隧道工程有限公司 红旗南路盾构项目部 二零一四年七月 目 录 1. 编制目的及编制依据 ......... ...
  • 盾构始发准备工作顺序
    1.盾构始发准备工作: 盾构掘进施工的竖井 始发工作井: 满足盾构掘进机安装和出洞施工的要求接收工作井: 盾构隧道掘进完成后进入接收井,满足盾构拆卸或转场吊装移位的工作空间要求 竖井施工方法: 沉井法.地下连续墙围护.钢板桩围护 ⑴凿除洞门 ...
  • 洞门施工方案
    目录 一.编制依据 ............................................ 1 二.工程概况 ............................................ 1 (一)工程概述 . ...
  • 绿化施工方案
    杭黄铁路先期开工段站前Ⅱ标项目经理部 绿 化 施 工 方 案 编制: 审核: 批准: 中铁十一局集团杭黄铁路HHXQZQ-Ⅱ标项目经理部一分部 二〇一七年三月 目 录 1. 编制依据 ............................ ...
  • 铁路隧道施工组织设计(毕业设计)
    绪论 随着我国铁路建设事业的蓬勃发展,铁路隧道已经越来越得到国家的重视.在贯穿我国山区的新建铁路线上,修建了大量的隧道,使我国铁路隧道的座数和总延长量,都跃居为世界各国的前列,同时还积累了丰富的经验,拥有了较先进的技术,也为铁路隧道的设计提 ...
  • 王王区间盾构接收应急预案
    武汉市轨道交通三号线土建工程第十标段 王-王区间盾构接收应急预案 编制: 日期: 审核: 日期: 批准: 日期: 中国中铁一局集团有限公司 武汉市轨道交通三号线土建工程第十标段项目经理部 2013年9月 武汉市轨道交通三号线土建工程第十标段 ...
  • 王村公路隧道初步设计任务书1
    专业名称: 教研室(系)主任: 批准日期: 西安工业大学毕业设计(论文)任务书 院(系): 建筑工程学院 专业: 土木工程 班级: 学生姓名: 二.毕业设计(论文)工作自 2012 年 月 日起至 2012 年 月 日止 三.毕业设计(论文 ...
  • 上海豫园.城隍庙.老街导游词
    一.豫园 导游指南:大假山景区-万花楼景区-点春堂景区-会景楼景区-玉玲珑景区-内园景区 站在门口讲解(顺时针方向): 东面:书画楼(南.上海画派的发祥地.现为小卖部).得月楼(北.楼为二层,西近荷花池,取"近水楼台先得月&quo ...
  • 隧道防水排水施工专项方案
    榴桐寨隧道防排水专项施工方案 1 编制依据 1.1.新建铁路成都至兰州线隧道施工设计图纸: 1.2.<高速铁路隧道工程施工质量验收标准>TB10753-2010: 1.3.<高速铁路隧道工程施工技术指南>铁建设[20 ...
  • 地铁盾构瓦斯隧道通风技术研究
    市政·交通·水利工程设计 Municipal ·Traffic ·Water Resources ·Engineering Design [文章编号]1007-9467(2010)07-0111-03 地铁盾构瓦斯隧道通风技术研究 (中铁一 ...